The New Airport Line of the Guangzhou
No. 3 Subway will be 30.8 kilometers long
and will have 10 stations. It starts from
Guangzhou East Railway Station, via Yantang,
Meihua Garden, Nanfa Hospital, Tonghe, Yongtai,
Jiahe, Longgui and Renhe stations, to arrive
at New Airport. There will be a south and
a north station at New Airport. The section
is scheduled to start construction in the
middle of 2006 and be completed in 2009.Due
to the complex geological situation of roads
leading to the new airport, the sections
between Yantang Station and Tonghe Station
and between South and North stations will
go underground. The section from Longgui
Station to Renhe Station will be built at
ground level with the rest on a viaduct.
The ground-level section will be 1.57 kilometers
long and the rest will have a total length
of 17.03 kilometers.The new subway will
have a designed maximum speed of 120 km
per hour. The trains will each have six
carriages. The New Airport Line is scheduled
to complete the initial phase, mid-term
phase, and long-term phase in 2012, 2019,
and 2034 respectively. The maximum one-way
passenger turnover will be about 2 million
in a peak hour.Construction of the subway
is scheduled to start in mid-2006 and be
completed at the end of 2009. The tunnel
construction of the South Station and the
1.73-km-long section between both ends has
been completed together with the first phase
construction of the new airport.The completion
of the New Airport Line, together with the
No.3 Subway, will form an express transport
system between the airport and southern
areas and will provide great convenience
for people in the Pearl River Delta to travel
by air.
|